5.1 Critical path analysis
Topic 5 · Topic 5: Discrete models

What this note covers

  1. Slack time: the outline's formula, exactly as written
  2. A worked project: slack for every task
  3. Interpreting slack: what one day of slack actually buys
  4. Crashing: shortening tasks to reduce the completion time
  5. Assumptions of the critical path model
  6. Reasonableness of results in context
  7. How this is examined in the SACE paper and what separates a top answer

7 sections · 12 key terms & formulas · 6 common mistakes

Included in the SACE General Mathematics Mastery Pack

20 full-length practice exams with worked solutions, 20 revision notes, 64 practice questions and 200 flashcards.

Unlock General Mathematics — $20

Preview a sample note and question free on the SACE General Mathematics hub →

SACE General Mathematics · revision note 17 of 20

Keep going