Slack time, crashing tasks and the assumptions and limitations of the model

5.1 Critical path analysis
Topic 5 · Topic 5: Discrete models

What this note covers

  1. Slack time: the outline's formula, exactly as written
  2. A worked project: slack for every task
  3. Interpreting slack: what one day of slack actually buys
  4. Crashing: shortening tasks to reduce the completion time
  5. Assumptions of the critical path model
  6. Reasonableness of results in context
  7. How this is examined in the SACE paper and what separates a top answer

7 sections · 12 key terms & formulas · 6 common mistakes

Common questions

What does the SACE General Mathematics note "Slack time, crashing tasks and the assumptions and limitations of the model" cover?

This note has 7 sections on Slack time, crashing tasks and the assumptions and limitations of the model. It includes 12 key terms and formulas, plus 6 common mistakes. It covers Topic 5, Topic 5: Discrete models. The full section list is shown under “What this note covers”.

Is this SACE General Mathematics note free to read?

A free sample extract is on the SACE General Mathematics hub. This note and the other 19 unlock with the SACE General Mathematics Mastery Pack, one payment, no subscription.

Included in the SACE General Mathematics Mastery Pack

20 full-length practice exams with worked solutions, 20 revision notes, 64 practice questions and 200 flashcards.

Unlock General Mathematics — $40

Preview a sample note and question free on the SACE General Mathematics hub →

SACE General Mathematics · revision note 17 of 20

Keep going