SACE General Mathematics exam: Mon 2 Nov, 1:30pm — 23 days away

ATARMAxxing · General Mathematics

SACE General Mathematics Practice Questions

64 exam-style questions · full worked solutions

The 64 practice questions inside the SACE General Mathematics Mastery Pack, grouped by area of study. Every question comes with a full worked solution.

  1. Topic 3: Statistical models22 questions · 45 marks
    • Multiple choice × 16
    • State × 1
    • Interpret × 1
    • Explain × 1
    • Calculate × 1
    • Predict × 1
    • Show that × 1
  2. Topic 4: Financial models21 questions · 43 marks
    • Multiple choice × 16
    • Calculate × 1
    • Show that × 1
    • Justify × 1
    • Discuss × 1
    • State × 1
  3. Topic 5: Discrete models21 questions · 43 marks
    • Multiple choice × 16
    • Calculate × 1
    • Draw × 1
    • Explain × 1
    • Complete × 1
    • Hence × 1
Sample question
A community hall refurbishment consists of seven tasks. The duration of each task, in days, and its immediate predecessors are: A, 5, none; B, 3, none; C, 6, A; D, 4, A and B; E, 2, C; F, 7, D; G, 3, E and F. Calculate the minimum completion time for the refurbishment, state the critical path, and calculate the slack time for each of tasks B, C and E.
Show the worked answer

Answer: Worked solution

Forward scan (earliest starting times, in days): EST(A) = 0 and EST(B) = 0; EST(C) = 0 + 5 = 5; EST(D) = max(5, 3) = 5 because D waits for both A and B; EST(E) = 5 + 6 = 11; EST(F) = 5 + 4 = 9; EST(G) = max(11 + 2, 9 + 7) = max(13, 16) = 16. The project finishes at 16 + 3 = 19, so the minimum completion time is 19 days. Checking the paths confirms this: A–C–E–G = 5 + 6 + 2 + 3 = 16, A–D–F–G = 5 + 4 + 7 + 3 = 19 and B–D–F–G = 3 + 4 + 7 + 3 = 17. The critical path is the longest path, A–D–F–G. Backward scan (latest completion times, in days), starting from 19: LCT(G) = 19; LCT(E) = LCT(F) = 19 − 3 = 16; LCT(C) = 16 − 2 = 14; LCT(D) = 16 − 7 = 9; LCT(B) = 9 − 4 = 5. Slack time = latest completion time − (task time + earliest starting time). Task B: 5 − (3 + 0) = 2 days. Task C: 14 − (6 + 5) = 3 days. Task E: 16 − (2 + 11) = 3 days. So B may be delayed by up to 2 days, and C and E share 3 days of slack along the path A–C–E, without delaying the 19-day completion. Note that C and E do not each have an independent 3 days: they lie on the same non-critical path, so using C's slack removes E's.
Included in the SACE General Mathematics Mastery Pack

20 full-length practice exams with worked solutions, 20 revision notes, 64 practice questions and 200 flashcards.

Unlock General Mathematics — $20

Preview a sample note and question free on the SACE General Mathematics hub →

General Mathematics · 64 practice questions